E s C A L I B M I L L s M D s : s I T E s P I R A L s T A I R C A s E W I T H s I D E E X I T 7 EsCALIB MILLs MDs > 6 - Fit and bolt the barrier gate with M16x100 screw: the erection guardrail is positioned horizontally. > 7 - With slings attached to the 2 lifting rings, the topmost module is fitted. Bolt the 4 uprights together using M24 screws. > 9 - At the access levels, the guardrails are positioned so as to privilege access by the main face A (face names shown on the sticker). > 8 - Check that the stair tower has been anchored before unhooking the slings. Guardrails will be swung out of the way to allow access to the required level. ASTUCE 21 cm The last step used should ideally be placed 21 cm lower than the floor being serviced. “T OPMOST ” MODULE N.B.: The erection guardrail must not be used as a substitute for the barrier gate.