Touréchaf

24 TOURéCHAF > Fitting beams: grouting guardrails raised. Grouting beam... A deck should be fitted to the top of a tower for grouting beams. > Grouting for 4 beams. > Using the grouting guardrail: 1 m and 1.50 m grouting guardrails provide protection for workers while they are grouting beams. Advantages: > Easy and quick to use. >The guardrails are designed to fit around the beams. >Allow the towers to be moved. > Formwork round the joint: The grouting guardrail next to the beam can be lowered. Example: 1.00 x 1.50 m tower > Moving below the beams: 4 grouting guardrails lowered > Fitting 4 grouting guar- drails from the outside of the tower (tower height ≤ 2 frames). > Safe assembly and removal from a temporary deck level (tower height ≥ 3 frames). > Lifting by crane. Provide 4 additional slings to make it easier to attach from the deck. OR > Moving using trolleys Moving T O U R é C H A F : S H O R I N G T O W E R W I T H I N T E G R A L S A F E T Y S Y S T E M